Title:
|
Citywide Park Restroom Update and City Council Direction Regarding Ted Greene Park Priorities
It is recommended City Council receive and file an update on City park restroom conditions, with rehabilitation needs of $3,125,000, and consider the following options for Ted Greene Park Restrooms:
1) Direct staff to actively seek grant funding from outside sources for full restroom/concession stand replacement using shovel-ready plans and highlighting community support for improvements; or
2) Direct Staff to perform renovations including ADA compliance (not including the surrounding concrete pavement) and replace the roof at a cost of approximately $160,000. This would change each stall to a single occupancy restroom with a locking exterior door, update fixtures, and repaint, as well as replace the failing roof.
|