Title: Amend the FY 2026-27 CIP Budget and Award Construction Contract to Pavement Coatings Co. in the Amount of $465,970.75 for "Complete Streets Quick-Build - Park Avenue and Orange Grove Avenue," Project No. 68601, to Include All Base Bid Items It is recommended that the City Council take the following actions: 1) Adopt the following Resolution: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF POMONA, CALIFORNIA, AMENDING THE FY 2026-27 CAPITAL IMPROVEMENT PROGRAM (CIP) BUDGET BY ACCEPTING, INCREASING REVENUE ESTIMATES BY $41,636 AND APPROPRIATING $337,011, OF WHICH $41,636 COMES FROM THE SOUTHERN CALIFORNIA ASSOCIATION OF GOVERNMENTS (SCAG) GRANT FUNDS, AND $295,375 COMES FROM THE CANNABIS COMMUNITY BENEFIT FUNDS (STIIIZY) TO "COMPLETE STREETS QUICK-BUILD - PARK AVENUE AND ORANGE GROVE AVENUE," PROJECT FD428 CIP PROJECT FUND | CC2590 CIP | PROJECT NO. 68601; 2) Award a construction contract to Pavement Coatings Co. for "Complete Streets Quick Build - Park Avenue and Orange Grove Ave...
Attachments: 1. Staff Report - Complete Streets, 2. Attachment No. 1 – Construction Agreement, 3. Attachment No. 2 - Resolution 2026-87, 4. Attachment No. 3 - SCAG MOU Amendment No. 1
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

title

Amend the FY 2026-27 CIP Budget and Award Construction Contract to Pavement Coatings Co. in the Amount of $465,970.75 for “Complete Streets Quick-Build - Park Avenue and Orange Grove Avenue,” Project No. 68601, to Include All Base Bid Items

 

It is recommended that the City Council take the following actions:

 

1)                     Adopt the following Resolution:

 

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF POMONA, CALIFORNIA, AMENDING THE FY 2026-27 CAPITAL IMPROVEMENT PROGRAM (CIP) BUDGET BY ACCEPTING, INCREASING REVENUE ESTIMATES BY $41,636 AND APPROPRIATING $337,011, OF WHICH $41,636 COMES FROM THE SOUTHERN CALIFORNIA ASSOCIATION OF GOVERNMENTS (SCAG) GRANT FUNDS, AND $295,375 COMES FROM THE CANNABIS COMMUNITY BENEFIT FUNDS (STIIIZY) TO “COMPLETE STREETS QUICK-BUILD - PARK AVENUE AND ORANGE GROVE AVENUE,” PROJECT FD428
CIP PROJECT FUND | CC2590 CIP | PROJECT NO. 68601
;

 

2)                     Award a construction contract to Pavement Coatings Co. for “Complete Streets Quick Build - Park Avenue and Orange Grove Avenue,” FD428 CIP Project Fund | CC2590 CIP | Project No. 68601 to include all Base Bid items in the total amount of $465,970.75;

 

3)                     Find that the Project referenced above is categorically exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301(c) and that the proposed Project will not have a significant effect on the environment; and

 

4)                     Authorize the City Manager to execute the construction contract and any subsequent change orders on behalf of the City of Pomona.