Title: Amend FY 2025-26 Capital Improvement Program (CIP) Budget and Award Construction Contract to Letner Roofing Co. in the Amount of $229,500 for "Fourth Street PD Evidence Building Roof Structure Rehabilitation" It is recommended that the City Council take the following actions: 1) Adopt the following resolution: RESOLUTION NO. 2026-52 - A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF POMONA, CALIFORNIA, TO AMEND THE FY 2025-26 CAPITAL IMPROVEMENT PROGRAM BUDGET BY UNAPPROPRIATING $50,000 OF PREVIOUSLY APPROPRIATED GENERAL FUNDS FROM "PD ROOF DRAINAGE MODIFICATIONS" FD428 | CC2590 CAPITAL IMPROVEMENT PROGRAM (CIP) | WORKTAG: PROJECT 71115 AND REAPPROPRIATING THESE GENERAL FUNDS TO "FOURTH STREET PD EVIDENCE BUILDING ROOF STRUCTURE REHABILITATION," FD428 | CC2590 CAPITAL IMPROVEMENT PROGRAM (CIP) | WORKTAG: PROJECT 71123 2) Award a construction contract to the lowest responsive bid from Letner Roofing Co. for "Fourth Street PD Evidence Building Roof Structure Rehabilitation," FD428 |...
Attachments: 1. Staff Report - 4th St PD evidence building, 2. Attachment No. 1 - Resolution No. 2026-52, 3. Attachment No. 2 - Evidence Proposal Letner April
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

title

Amend FY 2025-26 Capital Improvement Program (CIP) Budget and Award Construction Contract to Letner Roofing Co. in the Amount of $229,500 for “Fourth Street PD Evidence Building Roof Structure Rehabilitation”

 

It is recommended that the City Council take the following actions:

 

1)                     Adopt the following resolution:

 

RESOLUTION NO. 2026-52 - A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF POMONA, CALIFORNIA, TO AMEND THE FY 2025-26 CAPITAL IMPROVEMENT PROGRAM BUDGET BY UNAPPROPRIATING $50,000 OF PREVIOUSLY APPROPRIATED GENERAL FUNDS FROM “PD ROOF DRAINAGE MODIFICATIONS” FD428 | CC2590 CAPITAL IMPROVEMENT PROGRAM (CIP) | WORKTAG: PROJECT 71115 AND REAPPROPRIATING THESE GENERAL FUNDS TO “FOURTH STREET PD EVIDENCE BUILDING ROOF STRUCTURE REHABILITATION,” FD428 | CC2590 CAPITAL IMPROVEMENT PROGRAM (CIP) | WORKTAG: PROJECT 71123

 

2)                     Award a construction contract to the lowest responsive bid from Letner Roofing Co. for “Fourth Street PD Evidence Building Roof Structure Rehabilitation,” FD428 | CC2590 Capital Improvement Program | Worktag: Project 71123 to include all Base Bid items in the total amount of $229,500; and

 

3)                     Authorize the City Manager to execute the construction contract and any subsequent change orders on behalf of the City of Pomona (City).